Surry Hills update

4 October 2017

Construction has started on the Surry Hills stop at Ward Park, with foundations now laid.

Important utility work is continuing at key locations along Devonshire Street, including the Crown Street intersection, between Crown and Bourke Streets and Elizabeth and Crown Streets. Work compounds in these areas are being moved while construction takes place on different sides of the zone. Businesses and residents will be informed in advance about any changes that may impact them.

The installation of the new roadway has started in Devonshire Street, between Chalmers Street and Elizabeth Street alongside the completed track. This will now be followed by footpath and kerb finishing work on either side of Devonshire Street. During this time, the new roadway may be used for pedestrian access, and traffic will be returned to this section of Devonshire Street at a later date. Transport for NSW is working closely with businesses to minimise the impacts of footpath and kerb work.