Randwick construction update

20 December 2016

Track slab construction has started on Alison Road, between Darley and Wansey roads, marking a significant milestone for light rail in Randwick. The first tracks are still on schedule for installation early in 2017.

The new temporary retaining wall to protect the upcoming track slab excavation on the northern side of Alison Road is almost complete, with attention now turning to the complex task of raising the pavement area of the southern side of Alison Road to match the level of the alignment.

Further east, heritage and utility investigation on the High Cross Park site proposed for the undergrounding of a new substation is now complete. Construction work on the new substation is scheduled to start mid-January 2017.